In order for the staff of the St. Louis Development Corporation (SLDC) to prepare a Chapter 99 or 100 Blighting Study and Plan, the information below must be submitted by the first of the month in which the Plan is to be considered by the respective Board.

Once a Blighting Study and Plan is prepared, it must be reviewed and approved by the LCRA and/or PIEA Board prior to submittal to the Board of Aldermen for consideration. The Plan must also be reviewed by the St. Louis Planning Commission. An advertised public hearing before the appropriate Committee of the Board of Aldermen is required prior to passage.

The LCRA/PIEA must advertise for developers, and potential developers may submit proposals. A developer for the project will then be designated by LCRA/PIEA Board.

The LCRA/PIEA will then enter into an agreement with the selected developer.

It is imperative that the potential developer be present at the LCRA/PIEA Board meeting at which it is designated developer, and at the Board of Aldermen public hearing.

SUMMARY OF INFORMATION REQUIRED BY THE ST. LOUIS DEVELOPMENT CORPORATION FOR PREPARATION OF A CHAPTER 99 OR 100 PLAN

  1. Legal description and map of property to be included in the Area ("Area").
  2. Ownership of property within the Area.
  3. Condition of buildings, if any on the property(s).
  4. Number of existing occupants of Area.
  5. Number of existing jobs in Area.
  6. Proposed objective of redevelopment (i.e. rehab, new construction).
  7. Proposed use of the property (building by building).
  8. Proposed zoning of the property needed to carry out plan.
  9. Proposed on-site parking (numbers and ratios).
  10. Proposed changes in street and alley patterns.
  11. Proposed number of new jobs, including type and salary range.
  12. Public improvements needed.
  13. Property acquisition required by potential developer or PIEA or LCRA.
  14. Relocation required: list all to be relocated and characteristics.
  15. Proposed time of initiation and completion of phases of project.
  16. Square footage of proposed new construction and/or rehabilitation and estimated cost.
  17. Proposed method of financing the project.
  18. One (1) set of photos of the property, front and rear. (May be color copies from Kinko's or similar).
  19. Letter of support from Alderman of the ward.
 Return to Step 3